Our Work / Content / Tasks / (60hrs) PortlandTech: Continue Building Portal (Jan. 16-31) (Mehrunnisa, Arsalan Javaid, Rohail)

Project:

Description

Complete a minimum of 15 articles a day for the PortlandTech project. This will provide 150 articles during the iteration. With us moving to two-person teams per portal, it's unclear if this goal is high or low, but we'll adjust accordingly.

Why?

To continue filling out the PortlandTech resource.

Done When

150 articles are complete. (Number could change once we know how the teams work out.)

Useful Links

>

Resource Estimate

Approximately 4 to 5 hours everyday (1 member)

Total :60 hours

Enough to complete Portal by the end of this iteration.

Task Evaluation

  • Evaluator:
  • How the task went:
  • Sign off Person:
  • Sign off Date: